Progress continues on Ronald H. and Verna June Meen Center for Science and Math

Progress continues on the construction of the Ronald H. and Verna June Meen Center for Science and Math at Tusculum College, with interior work continuing, including window installment.

According to David Martin, director of facilities for Tusculum College, exterior damp proofing and windows are complete with the exception of custom windows for the Board Room, which will be installed next week.

“The roof is dried in, metal panels and copper gutters are ongoing. Window trim and masonry in progress,” said Martin, adding that rough grading of the north lot is complete.

As work continues, drywall, insulation, drywall soffits and finishing are ongoing on all floors, and fire protection is 90 percent complete. Paint priming will begin in two weeks.

It is expected that the construction will be completed by the end of the year and will be ready for utilization when students return for spring semester 2017.

The Meen Center for Science and Math will be a four-story structure of approximately 100,000 square feet. Interiors include wings for biology, chemistry, mathematics, computer science and environmental science. There will also be lab space and research areas for both faculty and students.

The ground floor features the environmental science wing with a loading dock, as well as large general classroom spaces and classrooms equipped for distance learning programs. A large lecture hall will be included on the ground floor. Space is also allocated to house the Bachelor of Science degree program in nursing and at least one other graduate level health-related program.

Interior finishing and window installation at the Ronald H. and Verna June Meen Center for Science and Math